Search
RSS Feed
Previous News Topics

Entries in The Sanctuary (26)

Thursday
Apr252013

Pouring The Barn Floor

Construction crews at The Sanctuary continue to make noticeable progress between Andrew's video updates. This month's video, filmed in Woodland Park on March 7th, brings viewers a fresh look at the rapidly advancing project. As you watch Andrew in this installment, you will also see a flurry of activity in the background as workers prepare and pour the floor for the main level of the 90,000 square foot Barn.

For a recap of the project's advancement, be sure to check out Andrew's previous updates, which have included the arrival of the earth movers, the leveling of the land, the foundation excavation, the preparation for the basement walls, piping in the water, the completion of the basement support structure and the enclosure of the south-facing wall. Each of these videos documents the progress as Charis Bible College's new campus continues to take shape.

Workers prepare to lay the rebar floor support for the Barn floor. (Click to enlarge) Workers methodically lay the rebar across the entire span of the floor. (Click to enlarge)

Cement trucks provide a steady stream of cement for the pouring of the floor. (Click to enlarge) Many hands on deck working feverishly to spread the cement. (Click to enlarge)

One man guides the flow of cement as many others spread it evenly. (Click to enlarge) The floor is poured and leveled using a variety of tools. (Click to enlarge)

The pour continues as this worker guides the cement onto the rebar reinforced floor. (Click to enlarge) These machines are used to level and finish the floor's surface. (Click to enlarge)

This update was filmed on March 7th, to view the most recent video update visit the Sanctuary Construction Update page on the ministry's main website.

Thursday
Mar142013

The Barn's South Wall Erected 

In this video, filmed on site at The Sanctuary, Andrew brings viewers an update on the construction progress at Charis Bible College's new campus in Woodland Park. While much of the content in previous updates has featured the excavation and ground preparation for the first building, this video brings viewers an all new perspective as the Barn's exterior begins to take shape. Crews have completed the installation of the pre-cast sections of the South-facing wall, enclosing all four sides of the building. With the walls erected, steel workers have begun placing 300 tons of interior steel framing. Significant progress can be seen since Andrew's last update.

Crews begin to place the pre-cast walls on the southern side of the Barn. (Click to enlarge) Each section of pre-cast wall is maneuvered into place using a huge crane. (Click to enlarge)

Sections of the gabled end stand supported as the the walls are secured. (Click to enlarge) With the walls in place crews begin to lay the steelwork. (Click to enlarge)

Some of the 300 tons of steel waiting to be placed. (Click to enlarge) A bird's-eye view as the steel I-beam is lifted into place. (Click to enlarge)

Crews guide the steel into place by hand.
(Click to enlarge)
Andrew observes as crews work to enclose the basement. (Click to enlarge)

The chimney crew works high above the ground on scaffolding. (Click to enlarge) In the video Andrew describes the height of the chimney. (Click to enlarge)

 

This update was filmed on February 5th, to view the most recent video update visit the Sanctuary Construction Update page on the ministry's main website.

Thursday
Feb212013

Basement Support Structure Complete

In this short video update Andrew reviews the construction progress at The Sanctuary in Woodland Park, Colorado. After four months of work, the concrete support structure for the Barn, the first of Charis Bible College's new buildings, is in place. Crews worked diligently to prepare the base for the South-facing pre-cast wall of the basement and the interior steel framing of the structure. Much attention was also given to the new road system on the property to make way for the arrival of the pre-cast wall sections and the 260-foot-tall crane needed to erect the wall sections and 300 tons of steel. While most of the work accomplished since Andrew's last update is now underground, viewers are able to see many changes in the landscape as his camera crews move around the campus.

Workers constructing framing for the cement footings for the South-facing wall. (Click to enlarge) One of the 30 cement pad footings now buried under the floor of the Barn's basement. (Click to enlarge)

The elevator shaft covered by tarps.
(Click to enlarge)
The elevator shaft within the tarps pictured at left. (Click to enlarge)

The pre-cast walls ready to be delivered and erected.
(Click to enlarge)
The crane used to place the precast walls under construction. (Click to enlarge)

This update was filmed January 14th, to view the most recent video update visit the Sanctuary Construction Update page on the ministry's main website.